Ashford

We completed a project for Wessex Water at a water treatment works in the south west.

The existing fiberglass Acid tanks had failed also the floors pipework and acid dosing system was in needed refurbishment.

We decanted the old tanks and associated pipework dosing skids.

These items were removed from site by our waste carriers.

Wessex Waters civil arm renewed the damaged floors.

We then installed two new stainless-steel tanks with all new valve pipework and wiring.

We purpose built new acid dosing cabinets with new pumps all stainless-steel pipework.

Once complete we handed back to Wessex Water.

Do you have a similar project coming up?